Rooppur Connects Grid for Second Test
Published : 11:33, 23 November 2026
The Rooppur Nuclear Power Plant has resumed experimental electricity supply to Bangladesh's national grid for the second time, injecting between 300 and 350 megawatts at 10:20am on Monday, November 23.
Dr Md Kabir Hossain, project director of the Rooppur Nuclear Power Plant construction project, confirmed the development.
He said the latest trial run would continue for 10 to 24 hours. During this period, engineers will conduct technical tests to assess the plant's generation system and its operational coordination with the national grid.
The facility first began experimental power transmission to the national grid on November 17 at 3:16pm. Approximately 350 megawatts of electricity were supplied during that initial test.
Monday's operation marks the second phase of the experimental grid connection, following the earlier trial. The latest round of testing is intended to evaluate the performance of the plant's electricity generation system and its ability to operate in coordination with the national grid.