Adani’s 800MW Power Plant Unit in Jharkhand to Shut Down for 25 Days
Published : 20:49, 25 November 2026
An 800-megawatt unit of Adani Power’s Godda power plant in Jharkhand, India, is set to shut down for 25 days for annual maintenance. The unit will stop generating electricity from midnight on Wednesday (November 25) and is scheduled to resume operations on December 18.
In a statement sent to the media on Wednesday, Adani Power said the shutdown had been planned in advance as part of the plant’s routine maintenance programme. During the period, the unit will undergo necessary inspections, equipment servicing and preventive maintenance. The company said it had obtained approval from the Bangladesh Power Development Board (BPDB) on October 26.
The coal-fired Godda power plant has a total generation capacity of 1,600MW, with each of its two units capable of producing 800MW. Under the power purchase agreement, however, the plant is required to supply 1,496MW of electricity to Bangladesh.
In November 2017, the BPDB signed a 25-year power purchase agreement with Adani Power (Jharkhand) Limited. Adani built the plant at a cost of $2 billion to supply electricity to Bangladesh. Its first unit began supplying power to the national grid on March 9, 2023.
The shutdown comes as electricity demand declines with the arrival of winter. According to the report, data from the National Load Despatch Centre (NLDC) show that electricity imports from India increased by around 37 per cent during the first 15 days of November compared with the same period in October, despite a decline in demand and domestic generation.
NLDC statistics show that Bangladesh imported an average of 33.6 million units of electricity per day from India in October. The daily average rose to 46 million units in November.
At peak demand on the evening of September 9, Adani supplied 1,430.06MW of electricity to Bangladesh. After the unit was shut down, supply fell to 691.44MW on September 10.